The CSB issues safety recommendations to prevent the recurrence or reduce the likelihood or consequences of similar incidents or hazards in the future. Recommendations are issued to a variety of parties, including government entities, safety organizations, trade unions, trade associations, corporations, emergency response organizations, educational institutions, and public interest groups. Recommendations are published in CSB reports and are closed only by vote of the Board. The CSB tracks all recommendations and communicates regularly with recommendations recipients to ensure that the recommended corrective actions are implemented. For more information, see Frequently Asked Questions about CSB recommendations.
2003-01-I-MS-10
Amend the Technical Specifications guidelines in the Responsible Care Management System to explicitly require facilities to identify findings and lessons learned from process hazard analyses and incident investigations in one unit and apply them to other equipment that processes similar material. Status: Closed - Acceptable Action
Amend the Technical Specifications guidelines in the Responsible Care Management System to explicitly require facilities to identify findings and lessons learned from process hazard analyses and incident investigations in one unit and apply them to other equipment that processes similar material.
2003-01-I-MS-11
Ensure that ACC members understand the audit requirements of Responsible Care and accurately identify and address gaps in facility process safety programs. Status: Closed - Acceptable Action
Ensure that ACC members understand the audit requirements of Responsible Care and accurately identify and address gaps in facility process safety programs.
2003-01-I-MS-12
Communicate the findings of this report to your membership. Status: Closed - Acceptable Action
Communicate the findings of this report to your membership.
2003-01-I-MS-2
Establish a program for conducting process hazard analyses of processes involving reactive materials. Status: Closed - Acceptable Action
Establish a program for conducting process hazard analyses of processes involving reactive materials.
2003-01-I-MS-3
Evaluate the need for layers of protection and install appropriate safeguards, such as alarms and interlocks, to reduce the likelihood of a runaway reaction and catastrophic release of material. Status: Closed - Acceptable Action
Evaluate the need for layers of protection and install appropriate safeguards, such as alarms and interlocks, to reduce the likelihood of a runaway reaction and catastrophic release of material.
2003-01-I-MS-4
Review and revise as necessary procedures for units that process highly energetic material, effectively communicate the updated procedures, and train workers appropriately. Revised procedures should include: Specific steps for isolation of energy sources. Warnings and cautions concerning process chemicals and consequences of deviations from operating limits. Critical operating limits and guidance when the limits are exceeded. Instruction on how to perform a shutdown for all foreseeable causes, to ensure proper isolation, and to continue monitoring critical parameters (such as temperature) while the column is shut down; in addition, review conditions under which material must be deinventoried (such as during extended shutdowns). Status: Closed - Acceptable Action
Review and revise as necessary procedures for units that process highly energetic material, effectively communicate the updated procedures, and train workers appropriately. Revised procedures should include: Specific steps for isolation of energy sources. Warnings and cautions concerning process chemicals and consequences of deviations from operating limits. Critical operating limits and guidance when the limits are exceeded. Instruction on how to perform a shutdown for all foreseeable causes, to ensure proper isolation, and to continue monitoring critical parameters (such as temperature) while the column is shut down; in addition, review conditions under which material must be deinventoried (such as during extended shutdowns).
2003-01-I-MS-5
Conduct a facility-wide survey of pressure vessels to ensure that all equipment that processes reactive materials has appropriate overpressure protection. Status: Closed - Acceptable Action
Conduct a facility-wide survey of pressure vessels to ensure that all equipment that processes reactive materials has appropriate overpressure protection.
2003-01-I-MS-6
Identify equipment critical to safe operation of processes containing reactive materials. Upgrade the maintenance program and establish inspection schedules to ensure the integrity of such equipment. Status: Closed - Acceptable Action
Identify equipment critical to safe operation of processes containing reactive materials. Upgrade the maintenance program and establish inspection schedules to ensure the integrity of such equipment.
2003-01-I-MS-7
Survey and take appropriate action to ensure that buildings occupied by plant personnel are of adequate construction and are located so as to protect people inside in the event of an explosion in equipment processing reactive materials. Status: Closed - Acceptable Action
Survey and take appropriate action to ensure that buildings occupied by plant personnel are of adequate construction and are located so as to protect people inside in the event of an explosion in equipment processing reactive materials.
2003-01-I-MS-1
Conduct audits to ensure that the First Chemical Pascagoula facility addresses the issues detailed below. Communicate results of these audits to the workforce. Status: Closed - Acceptable Action
Conduct audits to ensure that the First Chemical Pascagoula facility addresses the issues detailed below. Communicate results of these audits to the workforce.
2003-01-I-MS-8
Update the community notification system to: Immediately alert residents in the Moss Point community when an incident occurs that could affect their health and safety. Determine when a community response should be initiated. Communicate the nature of the incident and the appropriate response by residents. Alert residents when the incident is over (i.e., the all-clear has sounded). Status: Closed - Acceptable Action
Update the community notification system to: Immediately alert residents in the Moss Point community when an incident occurs that could affect their health and safety. Determine when a community response should be initiated. Communicate the nature of the incident and the appropriate response by residents. Alert residents when the incident is over (i.e., the all-clear has sounded).
2003-01-I-MS-9
Conduct an awareness campaign to educate residents on the proper steps for a shelter-in-place and orderly evacuation. Status: Closed - Acceptable Action
Conduct an awareness campaign to educate residents on the proper steps for a shelter-in-place and orderly evacuation.
2003-01-I-MS-13
Amend the Technical Specifications in the Responsible Care Management System to explicitly require facilities to identify findings and lessons learned from process hazard analyses and incident investigations in one unit and apply them to other equipment that processes similar material. Status: Closed - No Longer Applicable
Amend the Technical Specifications in the Responsible Care Management System to explicitly require facilities to identify findings and lessons learned from process hazard analyses and incident investigations in one unit and apply them to other equipment that processes similar material.
2003-01-I-MS-14
Ensure that SOCMA members understand the audit requirements of Responsible Care and accurately identify and address gaps in facility process safety programs. Status: Closed - No Longer Applicable
Ensure that SOCMA members understand the audit requirements of Responsible Care and accurately identify and address gaps in facility process safety programs.
2003-01-I-MS-15